This week's Christmas bulletin contained an excerpt about the status of the project, including an erroneous statement about the building being 108,000 sqft. Therefore, this week, while you peruse photos of our progress in the shortened construction week, we offer "Campus Project By the Numbers":
  • Total Project Cost: $4,200,000

  • Parish Center Size: 20,741 square feet

  • Hall: Seats 250-400. Dance floor, beverage area, 2 serving lines

  • Kitchen: Yes, 1300 sqft including storage. Fully equipped

  • Second Floor: No, but can be added in future

  • Basement: Unfinished, under office area only. Elevator access

  • Garage: 4-car, plus maintenance bay

  • Heatings & Cooling: 3 Rooftop units, Radiant Heat perimeter

  • Protection: Fire & Burglar Alarms, Keycard Access

  • Technology: Central server, Audio/Visual in Hall and Library

  • Number of Offices: 10, plus up to six workstations in main office

  • Stained Glass Windows: 8, re-used from Blessed Angela Room

  • Large Conference Rooms: 1, modular furniture, seats 20-25

  • Small Conference Rooms: 2 public, 1 staff. Each seats 8-12.

  • Pastoral Library: 25' x 30' with bookcases and casual furnishings


  • It's all going to add up to tremendous opportunity for our parish!