Week 2 - Site Work Continues
Last week, we had the first of our dirt moved, and this week we've already got a substantial hole dug.
It's interesting to see the cement chunks coming up that were part of the old convent basement; when the convent was torn down, the basement was simply filled in. As part of the construction, this has to come out.
Pictures of the progress in Week 2 can be seen in our album.
In other news, our furniture spec should be going out late this week. The goal is to have responses back by the middle of May.
The parish staff is frantically preparing to vacate the old parish center by the end of May. They will be taking up temporary locations around the campus, including the Youth Room in the grade school. This will allow us to start the asbestos abatement early enough to have the building come down in August. That will certainly help the parking situation!